Sierra Encore Duet Implementation Plan

Broward College's next generation library services platform

Project Schedule - 2018 rollout

SIERRA AND ENCORE DUET IMPLEMENTATION WORK SUSPENDED:

  • FALSC and Innovative have mutually agreed that they will not go live with Sierra Encore in July 2018.  They are working together exploring ways to allow them to move forward in a different direction on the implementation project.


August 2017

  • Broward employee Sierra accounts created DONE - check with Rich if you do not have your credentials or if you have new hires who need logins.

October - November 2017

  • Production system available for testing
  • October 9 - October 20: Phase 1 of comprehensive testing
  • November 8, 10:00 Systems Working Group Webinar on November 8 at 10 am ET to give an intro to Create Lists. Collaborate link
  • November 8, 1:00 - UBorrow Workflows Webinar on November 8 at 1:00 pm ET. Use the Collaborate Link to join.
  • November 14 - December 2: Phase 2 of comprehensive testing

December 2017

  • December 1 - next Sierra release DONE 
  • December 8 - next Encore Duet release
  • Sierra Web browser available
  • Completion of development and implementation of new software at III
  • FALSC checkpoint - GO/NO GO decision for July go-live

Spring 2018

  • Refresher training
  • January - May: Customer readiness review. Local testing and workflow analysis,
  • May - July: Production go live schedule (TBD)

Deliverables - 2018 rollout

Sierra Encore Duet rolls out July 2018.

Deliverables

  • Manuals available to staff for reference
  • Internal policies and procedures guides updated
  • Library, ASC, Reserves websites updated
  • D2L updated
  • Libguides updated 
  • Single sign on integration with D2L; "Library Resources" link modified to not go through IT's custom SSO program
  • Single sign on integration with MyBC; "Library Resources" link modified to not go through IT's custom SSO program
  • Clean up ucl.broward.edu to remove homegrown SSO error handler
  • Communications -- see communications tab
  • All links to Mango catalog converted to Encore/Duet
  • All links to electronic resources converted to new proxy server

Status Meetings - 2018 rollout

Monday, 11-noon, Room 315, every other week.

9/25/17 - kickoff II

10/9/17 - Testing starts, access, ID

10/23/17 - Review test results. Plan next steps.

11/6/17 - Interlibrary Loan overview (Grushy)

11/20/17 - Testing Phase 2 - status updates, Q&A

12/4/17 - Testing Phase 2 - summary, review, feedback

 

Original Schedule - DONE

  • August – December 2016: Additional training for FALSC staff and working groups; Data cleanup by BSLW; Iterative review of data and parameters
  • September 15 - October 15 Quality control, initial review of profile and test loads (data and parameters) using April data DONE
  • October 3, location code profiles due to FALSC DONE
  • October 15-30 Sierra server down; first production load with new profiles (April data) DONE
  • January 2017: Reload data from BSLW to newly setup train/test server  DONE
  • February – July 2017:
    • Iterative review of profile and test loads (data and parameters)  IN PROGRESS
  • February 6, 2017: Sierra Web Client release 1.0. Chrome is the required browser. DONE
  • February 21, 2017: Report preliminary priorities due back to Rich DONE
  • February 28, 2017: Report Survey due back to FALSC (Rich) DONE
  • February - April 2017
    • self-directed training via Training Tracks (all)
  • March 3 - deadline for FTP testing (2624499) DONE
  • March 3 - deadline for opening ports for new servers (Dan) DONE
  • March 23 - deadline for responding to Reserves survey (Rich) DONE
  • March 27: design review for Encore Duet user interface DONE
  • March 28 - deadline for responding to Joint Use survey (Rich) DONE
  • March 29 - 10:00am - 17/315 - Encore Facets webinar DONE
  • April 2017
    • April 6: 2:00, 17/315 - FALSC webinar ILS: Encore Customization Options– Patron Page Functions, Tagging, Promotion of Titles". POSTPONED
    • April 10: 11:00, 17/315 - design review of Encore Duet facets DONE - configuration sent to FALSC
    • April 11: 3:00, 17/315 - EBSCO webinar, EBSCOadmin (search modes, limiters, facets and database customizations) DONE - configuration updated in EBSCOadmin
    • April 20: 1:30-2:30, FALSC webinar: Encore Overview and Q&A webinar in 17/315 DONE
    • April 25 - Cataloging face to face training at Broward College (participants listed on Training tab) DONE
    • April 26 - Circulation 1 face to face training at Broward College (participants listed on Training tab) DONE
    • April 27 - Circulation 2 face to face training at Broward College (participants listed on Training tab) DONE
  • May 2017
    • May 2 - Acquisitions 1 face to face training at Palm Beach State College (participants listed on Training tab)   DONE
    • May 3 - Acquisitions 2 face to face training at Palm Beach State College (participants listed on Training tab)  DONE
    • May 3: 2:00-3:30, EBSCO EDS/Encore Duet Linking to Full Text webinar in 17/315 DONE
    • May 4 - Reports face to face training at Palm Beach State College (participants listed on Training tab)  DONE
    • May 4: 10-noon, FALSC Sierra Options and Settings webinar in 17/315 DONE
    • May 5 - Electronic Resource Management face to face training at Palm Beach State College (participants listed on Training tab)  DONE
    • May 16: 2:00pm - 17/315 - EBSCO Full Text Finder webinar (Holdings Management in EBSCOadmin) DONE
  • June 2017
    • June 9: Room 104, Report Writing In-House Training POSTPONED
  • July 2017
  • August 28, 2:00-3:30, EDS/Encore Duet Usage Statistics in 17/315. Open to everyone.POSTPONED
  • Post go-live
    • Curriculum Builder integration into D2L
    • Short Story Index in A-Z Databases retire http://uclprintvm/ssindex/ DONE
    • Play Index in A-Z Databases retire http://uclprintvm/drama/ DONE